Since graduating in 2011, I have been working in costume for the Film and TV industry, starting as a trainee on the ITV show, ‘Vera’, and more recently as Principal Supervisor on the new adaptation of ’Sense & Sensibility’. I have always had a particular love of period drama, and through this job I get […]

TEST

TEST
TEST
TEST

Hartlepool Film and TV village construction timeline revealed

by Rachel Smith | Oct 6, 2025 | Hartlepool Events, Latest News, Stage & Screen Faculty

2 min read

Timescales for a £33.5m project to expand Hartlepool’s film and TV studios and create a new production village have been revealed according to a news report by the BBC.

According to the story on the BBC news website the timetable follows the announcement about expansion plans for The Northern Film & TV Studios, which neighbours The Northern School of Art’s Church Street degree-level campus in Hartlepool, and the development of a screen industries production village which were approved last month.

Proposed entrance to the Production Village credit Hartlepool Council and TVCA

The BBC news story continues as follows.

The technical designs are due to be completed in February 2026, with the main manufacturing and construction period expected to start in August of that year.

Building work is expected to be completed by November 2027, with the site “operationally ready” by spring 2028.

Work will include repairs and renovations to the Grade II listed vacant Shades building, which councillors heard will be the “arrival point” and “spiritual home of the production village”, the Local Democracy Reporting Service said.

The latest meeting of the Hartlepool Borough Council’s economic growth and regeneration committee heard the approval marked “a major milestone for the project” and received an update of what would come next:

A computer-generated image of how the Production Village may look. Credit Hartlepool Council and TVCA

  • October 2025 – demolition of a car wash in Whitby Street and “opening up works” on production village assets
  • February 2026 – technical designs, including full architectural and engineering details, to be finalised
  • February to July 2026 – tender procurement stage
  • August 2026 – main manufacturing and construction period expected to begin
  • November 2027 – construction expected to be completed
  • December 2027 – final certificates and handovers carried out
  • Spring 2028 – site “operationally ready”

The project is being led by Hartlepool Borough Council, in partnership with The Northern School of Art, Tees Valley Combined Authority and North East Screen.

The £33.5m is coming from levelling up funding and the Tees Valley Investment Zone Fund.

To read the full story click here